The prefabricated bathroom pod can be positioned from above (before each floor slab) during the construction of the building, or from the side (horizontally through rolling) once the building’s structural frame is completed and before starting the installation of the external walls and systems.
POSITIONING FROM ABOVE
The bathroom pods are installed during the construction of the building’s structure and positioned directly on the floor before the upper slab is laid. This solution is easily applicable when using self-supporting floor slabs that do not require temporary supports.
SIDE INSTALLATION THROUGH ROLLING
The bathroom pods are installed after the construction of the building’s structure, before the installation of external walls and systems. The bathroom pod is brought to the floor on external platforms and then rolled into its final position. In this case, the required height clearance and minimum width for passage along the route must be checked.